Current accessibility
🤔 SFA to some platforms
No SFA to platforms
2-3
SFA to these platforms only
Possibly 1, 4 —*not sure* as NRE website has missing data
Date works started
Aug 1, 2024
Date is at month level
Date SFA planned to open
Aug 1, 2025
Date is at month level
Platforms – in regular use
1-4
Difficulties faced
Shortage of funding
Success factors
Challenged under Equality ActFacilitated by electrification works modsLocal politiciansORR
Upgrade scope
New liftsElectrical works
Property
Dropdown value
Value
Flags
Title (not in use)
Property
Dropdown value
Text value
Funding
Date
Flags
Value
Title (not in use)
About this station
Platforms
Current accessibility
Photos
Progress
Network Rail said:
The Bromsgrove Electrification project reconstructed Barnt Green station footbridge, to a new height over a metre higher than the old footbridge, to allow sufficient vertical headroom for the overhead electrification equipment. During the delivery of electrification scheme, cost increases appeared which led to the lifts being removed from scope, and passive provision only being allowed for.
The non-provision of lifts was challenged by the ORR and local politicians as not being in line with the Equality Act 2010. Therefore it was agreed between NR and the DFT that this project will install the lift access.
Continued:
The Project will deliver the following outputs
• Construction of three lifts to existing station footbridge, including foundations, lift chambers, brickwork/cladding, equipment rooms
• Installation of new sub-station power supply (insufficient capacity on existing power supply)
• Installation of an under-track crossing (UTX) or similar for associated cabling
• Upgrade of earthing and bonding installation on Platforms 3&4 to provide PAN102 & BSEN50122 compliance
enhancements delivery plan June 2024 (see links), page 15
Links
Official sources
Page 15